Project Milestones:

  • Project Kickoff: July 2018
  • 75% Design Plans In Hand Submittal: January 2019
  • 95% Design Pre-PS&E Submittal: September 2019
  • Final Design and Construction Bid Package Ready: August 2020
    • ROW acquisitions, August 2020
    • Environmental permits were received July 2020
  • Construction Start: Fall 2020
  • Construction Completion: Fall 2022